CMS Bush

Construction Management Specialists

  • About
    • Our Story
    • Core Values
    • Projects
    • Blog
  • Services
    • Our Approach
    • Development
    • Negotiated Work (Design / Build)
    • Pre-Construction
    • Construction Management
  • Renovations
  • Commercial
    • Steel Buildings
    • Value Added Services
  • Project Delivery
    • Our Process
    • Competitive Bidding
    • Project Staffing
    • Partner Alignment
    • Execution Planning
    • Project Controls
      • Daily Reporting
      • Quality Assurance
      • Document Control
    • Project Safety
    • Subcontractor Relations
    • Sustainable Practices
    • Project Close-Out
  • Contact
  • Blog
    • Construction
    • Construction Management

Outline of Document Control Procedures

As the General Contractor or Construction Manager (typically playing both roles), we assume responsibility for project documentation and control, managed by proprietary process.

Permitting

We submit construction documents for plan review and permitting, including filing of the Notice of Commencement if needed.

Construction Documents

We distribute Construction Drawings and Addendums to the subcontract trades. Permitted drawings are posted on the construction site by the GC. We track any revisions, ensuring that they are submitted to plan review and distributed to the subcontract trades in a timely fashion.

Requests for Information

RFI’s may be issued by the subcontractors to the GC or by the GC for various reasons, not limited to need for additional clarification on construction details, finishes, or product specifications. Often times these are initiated by field conditions that do not match the construction drawings. It is our responsibility to the RFI with the subcontractor, summarize the issue, and issue a formal request with documentation to clearly communicate and identify the issue.

We direct the formal RFI to the Owner and Design Team, tracking the issue to verify an answer is provided in a timely fashion so as not to incur a delay and then formalize, distribute, and archive the RFI response. This creates a historical log of any deviations from the construction documents.

Submittals

Prior to ordering any materials or fabrication of custom items, the GC will collect and issue formal submittals of product data specifications, shop drawings, and safety data sheets. These are issued to the Owner and Architect for review and comment. The GC tracks the responses to ensure comments are incorporated and that materials are ordered accurately and in a timely fashion. Submittal documentation is compiled and archived for the Owner’s records.

Change Requests and Orders

Through the course of a construction project, Change Requests may be issued by the Owner, General Contractor, or Subcontractor due to a change in preferences, change in budget circumstances, desire for additional work, design errors, or hidden or unforeseen conditions that require deviation from the construction documents.

We will record and track all change requests, converting approved change requests into formal change orders. A change order will be accompanied with the original change request, confirmation of approval, pricing information and any subsequent submittal documentation required.

Pay Applications and Lien Waivers

On a regular basis, outlined within the contract documents, we will collect subcontractor payment applications and conditional lien waivers. We review all subcontractor payment applications for accuracy and consistency. The Owner receives a single payment application from the GC determined by the current progress of the project on the scheduled payment period. Conditional Lien Waivers are provided with each payment application.

Upon payment, the Owner will be issued an Unconditional Lien Waiver from the GC. We then distribute funds to the subcontractors. As a condition for payment, the subcontractors must submit an Unconditional Lien Waiver in the amount of the payment for themselves and any sub-subcontractors or suppliers. These Unconditional Lien Waivers are provided one month in arrears with the subsequent payment application.

  • Project Delivery
    • Competitive Bidding
    • Project Staffing
    • Partner Alignment
    • Execution Planning
    • Project Controls
      • Daily Reporting
      • Quality Assurance
      • Document Control
    • Project Safety
    • Subcontractor Relations
    • Sustainable Practices
    • Project Close-Out

Let’s Get to Work

We want to hear to about your project goals. Let's kick things off with a brief conversation.

Schedule Online
CMS Bush, Inc.

CMS BUSH, Inc
Lic. # CGC061650

© CMS Bush, Inc. All rights reserved.

Construction Office:

9100 Conroy – Windermere Road
Windermere, Florida 34786

P| (407) 316-8544

E| info@cmsbush.com

FOLLOW US

Facebook
LinkedIn